SE Migration Schedule
The following is a high-level overview of the key project dates and milestones for the SharePoint SE roadmap.
Migration Timeline
2024 Schedule
Q1
-
Confirm SharePoint SE as upgrade path from SP2016
Q2
-
Past migration review
-
Provision SE test environment
Q3
-
Create mock test site
Q4
- Kick-off migration project planning
2025 Schedule
Q1
- Asset Migration
- Perform test migration from 2016 to SE
- Freeze on website redesigns begins
Q2
-
Prepare for first agency website migration group
Q3
-
Begin agency website migrations
Q4
-
Continue agency website migrations
2026 Schedule
Q1
-
Continue agency website migrations
Q2
-
Complete agency website migrations
-
Website redesign freeze period ends